Coffrargile disposable formwork
Swipe to turn the page
To see the page exactly as printed, open it in the PDF. Open the PDF at page 7
Text of page 7
7 A2 A3 A4 A1 B1 C1 C2 C3 C4 C5 B2 B3 B4 B5 A5 1 2 Position the fi rst element to the upper left with respect to the work surface, making sure that the arrow is pointing up (Fig. 1). Unite the elements in sequence, by horizontal row, proceeding from the left towards the right and from the top downwards (following the direction normally used for writing), as shown graphically on the crown of each unit (Fig. 2). Dry assembly method 1 2 3 Row Row Row rst nd rd Fig. 1 - Dry positioning of the fi rst formwork, the arrow is facing the foundation curb. Fig. 2 - Dry positioning sequence of the modules by row. www.baygar.com