6 1 3 2 4 Installation Lay the interlocking male/female formworks directly on the dry ground, from left to right and top to bottom, ensuring that the arrow marked on the Coffrargile formwork is facing up. Placement of the reinforcing rods is above the formwork and above the foundation beams, according to the project. Place the Beton Up element above each leg to plug the hole and prevent the concrete from forming pillars. Casting of the reinforced concrete to form a load-bearing slab that is reinforced and supported with a cavity along the edges to accommodate the movements of the ground. To ensure a correct installation and perfectly created under-fl oor cavity please refer to the product’s usage requirements. Coffrargile and Beton Up installation Casting and smoothing www.baygar.com