Inicio Fichas técnicas Encofrado perdido y hormigón Encofrado no recuperable Coffrargile
Daliform
Encofrado no recuperable Coffrargile
Desliza para pasar de página
Para ver la página tal como está en el catálogo, ábrela en el PDF. Abrir el PDF en la página 7
Texto de la página 7
7 A2 A3 A4 A1 B1 C1 C2 C3 C4 C5 B2 B3 B4 B5 A5 1 2 Position the fi rst element to the upper left with respect to the work surface, making sure that the arrow is pointing up (Fig. 1). Unite the elements in sequence, by horizontal row, proceeding from the left towards the right and from the top downwards (following the direction normally used for writing), as shown graphically on the crown of each unit (Fig. 2). Dry assembly method 1 2 3 Row Row Row rst nd rd Fig. 1 - Dry positioning of the fi rst formwork, the arrow is facing the foundation curb. Fig. 2 - Dry positioning sequence of the modules by row. www.baygar.com